Allied Gold says Kurmuk project enters pre-commissioning phase, first gold due mid-2026
Share
Listen to the news
Allied Gold says Kurmuk project enters pre-commissioning phase, first gold due mid-2026
  • Allied Gold reported pre-commissioning has started at its Kurmuk Gold Project in Ethiopia, keeping first gold targeted for mid-2026.
  • Kurmuk remained on schedule and on budget, with construction focused on mechanical, electrical, instrumentation, control systems.
  • The project expects grid power before commissioning, with Ethiopian Electric Power advancing a transmission line to the site.
  • Post start-up output forecast at about 290,000 ounces a year for the first four years, averaging about 240,000 ounces a year over mine life.
  • In Côte d’Ivoire, an integrated plan extended Bonikro mine life to 2036, targeting about 120,000 ounces a year.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Allied Gold Corporation published the original content used to generate this news brief via GlobeNewswire (Ref. ID: 202606100753PRIMZONEFULLFEED9734823) on June 10, 2026, and is solely responsible for the information contained therein.

Disclaimer:This article represents the opinion of the author only. It does not represent the opinion of Webull, nor should it be viewed as an indication that Webull either agrees with or confirms the truthfulness or accuracy of the information. It should not be considered as investment advice from Webull or anyone else, nor should it be used as the basis of any investment decision.