-+ 0.00%
-+ 0.00%
-+ 0.00%
Strabag expands Kelag’s Wurtenspeicher dam, lifting storage to 5 million cubic meters
Share
Listen to the news
Strabag expands Kelag’s Wurtenspeicher dam, lifting storage to 5 million cubic meters
  • Strabag won a contract from Kelag to expand the Wurten reservoir in Carinthia’s Fragant hydropower complex.
  • Project lifts the dam by 7 meters, raising the storage target by 8.5 meters.
  • Reservoir capacity is set to rise to 5 million cubic meters from 2.7 million, increasing flexible hydropower output.
  • Construction started in spring 2025; main works are scheduled to finish in 2026, followed by remaining works in 2027.
  • Kelag put investment at about EUR 30 million.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Strabag SE published the original content used to generate this news brief on July 10, 2026, and is solely responsible for the information contained therein.

Disclaimer:This article represents the opinion of the author only. It does not represent the opinion of Webull, nor should it be viewed as an indication that Webull either agrees with or confirms the truthfulness or accuracy of the information. It should not be considered as investment advice from Webull or anyone else, nor should it be used as the basis of any investment decision.
What's Trending