District Metals posts corporate deck on Sweden Viken uranium-vanadium shale project
Share
Listen to the news
District Metals posts corporate deck on Sweden Viken uranium-vanadium shale project
  • District Metals highlighted a June 2026 PEA for the 100%-owned Viken uranium-vanadium alum shale project in Sweden.
  • After-tax NPV8% of US $2.88 billion; after-tax IRR of 46%; payback of 2.1 years; after-tax free cash flow of US $531 million per year.
  • Initial capex of US $876 million; 13-year Phase 1 mine life; 3.3 million lbs U3O8 per year; strip ratio of 0.2:1.
  • 2025 resource update cited 4,333 million tonnes inferred at 161 ppm U3O8 for 1,538 million lbs contained U3O8.
  • Share count as of June 16, 2026: 190,807,421 basic shares; 213,990,421 fully diluted.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. District Metals Corp. published the original content used to generate this news brief on July 13, 2026, and is solely responsible for the information contained therein.

Disclaimer:This article represents the opinion of the author only. It does not represent the opinion of Webull, nor should it be viewed as an indication that Webull either agrees with or confirms the truthfulness or accuracy of the information. It should not be considered as investment advice from Webull or anyone else, nor should it be used as the basis of any investment decision.