Sixty North Gold targets Mon Gold Mine production start this year in NWT
Share
Listen to the news
Sixty North Gold targets Mon Gold Mine production start this year in NWT
  • Sixty North Gold targets first gold production in 2026 from its wholly owned Mon Gold Mine near Yellowknife, Northwest Territories.
  • Site work started. Regulators cleared the mill pad. Road construction to the dry-stack tailings facility is set to begin within two weeks.
  • Revised mill design and construction plan filed for review. Remaining operating approvals hinge on management plans, led by water and groundwater requirements.
  • All mining and milling equipment, supplies, crews are on site. The planned mill rate is 100 tons per day.
  • Underground work intersected the A-Zone below historic stopes. A new DD-Zone was exposed in the main ramp.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Sixty North Gold Mining Ltd. published the original content used to generate this news brief via Newsfile (Ref. ID: 202607160942NEWSFILECNPR____20260716_305438_1) on July 16, 2026, and is solely responsible for the information contained therein.

Disclaimer:This article represents the opinion of the author only. It does not represent the opinion of Webull, nor should it be viewed as an indication that Webull either agrees with or confirms the truthfulness or accuracy of the information. It should not be considered as investment advice from Webull or anyone else, nor should it be used as the basis of any investment decision.