Ares Strategic Mining begins commissioning Delta, Utah fluorspar lumps plant
Share
Listen to the news
Ares Strategic Mining begins commissioning Delta, Utah fluorspar lumps plant
  • Ares Strategic Mining started commissioning its metallurgical fluorspar Lumps Plant at its Delta, Utah processing facility.
  • Four-week commissioning program began with the full plant powered up as an integrated system.
  • Ramp-up production is scheduled to start Aug. 15, 2026, using ore stockpiled at the Lost Sheep Mine.
  • The plant is designed to process Lost Sheep ore into metallurgical-grade fluorspar for U.S. steel customers.
  • Designed capacity is about 150,000 tonnes a year; initial metspar output is covered by existing five-year offtake agreements.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Ares Strategic Mining Inc. published the original content used to generate this news brief via TheNewswire (Ref. ID: 202607210730TNWSWRCACNPR_____1BglF3mJa) on July 21, 2026, and is solely responsible for the information contained therein.

Disclaimer:This article represents the opinion of the author only. It does not represent the opinion of Webull, nor should it be viewed as an indication that Webull either agrees with or confirms the truthfulness or accuracy of the information. It should not be considered as investment advice from Webull or anyone else, nor should it be used as the basis of any investment decision.