Kefi Gold and Copper's Tulu Kapi Gold Project in Ethiopia on Track for Commissioning in Late 2027
Share
Listen to the news
04:48 AM EDT, 08/04/2026 (MT Newswires) -- Kefi Gold and Copper (KEFI.L) said Tuesday that all key milestones at the Tulu Kapi gold project in Ethiopia are on track with the schedule. The gold and copper exploration and development company expects to start commissioning in late 2027, with full production from the open pit and process plant set for mid-2028. Kefi said activities in August have been focused on community resettlement and equipment procurement for the plant.
Disclaimer:This article represents the opinion of the author only. It does not represent the opinion of Webull, nor should it be viewed as an indication that Webull either agrees with or confirms the truthfulness or accuracy of the information. It should not be considered as investment advice from Webull or anyone else, nor should it be used as the basis of any investment decision.
What's Trending