United Utilities hits milestone on £48 million Knutsford stormwater storage upgrade
Share
Listen to the news
United Utilities hits milestone on £48 million Knutsford stormwater storage upgrade
  • United Utilities began a GBP 48 million upgrade in Knutsford to add storm-water storage, curb storm overflow operations, improve treated-water quality.
  • Project includes a 1.8 km underground storage tunnel with a 2 m diameter between Moor Pumping Station, Knutsford Treatment Works.
  • Tunnel boring reached a halfway milestone; scheme targets up to 5,500,000 liters of storm-water storage once completed.
  • Investment sits within the Big North West upgrade program, which plans more than GBP 13 billion of spending over four years.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. United Utilities Group plc published the original content used to generate this news brief on August 04, 2026, and is solely responsible for the information contained therein.

Disclaimer:This article represents the opinion of the author only. It does not represent the opinion of Webull, nor should it be viewed as an indication that Webull either agrees with or confirms the truthfulness or accuracy of the information. It should not be considered as investment advice from Webull or anyone else, nor should it be used as the basis of any investment decision.