Eneva starts commercial operation of Azulao I gas-fired power plant in Amazonas, securing R$ 278.3 million annual fixed revenue
Share
Listen to the news
Eneva starts commercial operation of Azulao I gas-fired power plant in Amazonas, securing R$ 278.3 million annual fixed revenue
  • Eneva received ANEEL authorization to start commercial operations of the Azulão I natural-gas thermal plant in Amazonas.
  • The plant has 295 MW contracted in ANEEL’s 2021 capacity reserve auction for 15 years starting Aug. 5, 2026.
  • Fixed annual revenue set at R$ 278.3 million, indexed to IPCA; variable revenue reference set at R$ 1,200.87/MWh, adjusted by JKM and FX.
  • Azulão I is the first operating asset in the Azulão 950 complex; Azulão II is scheduled to start in July 2027.
  • Azulão II contract secures fixed annual revenue of R$ 1.92 billion for 15 years, indexed to IPCA.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Eneva SA published the original content used to generate this news brief on August 04, 2026, and is solely responsible for the information contained therein.

Disclaimer:This article represents the opinion of the author only. It does not represent the opinion of Webull, nor should it be viewed as an indication that Webull either agrees with or confirms the truthfulness or accuracy of the information. It should not be considered as investment advice from Webull or anyone else, nor should it be used as the basis of any investment decision.