BGE wins Maryland approval for Brandon Shores retirement transmission upgrades
Share
Listen to the news
BGE wins Maryland approval for Brandon Shores retirement transmission upgrades
  • Exelon utility Baltimore Gas and Electric won Maryland PSC authorization to proceed with PJM-directed transmission upgrades tied to Brandon Shores, H.A. Wagner retirements.
  • Buildout targets December 2028 completion; includes new substations, expanded facilities, transmission rebuilds, added circuits within existing rights-of-way.
  • Project supports retirement of nearly 2,000 MW of coal generation in Maryland, reducing emissions while maintaining regional grid reliability.
  • Exelon utilities PECO, Pepco also directed by PJM to pursue transmission upgrades in their service areas to address plant-retirement reliability risks.
  • BGE estimates Maryland power imports could rise to 80% from about 40% once the plants retire, increasing supply-cost pressure on customers.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Exelon Corporation published the original content used to generate this news brief on August 07, 2026, and is solely responsible for the information contained therein.

Disclaimer:This article represents the opinion of the author only. It does not represent the opinion of Webull, nor should it be viewed as an indication that Webull either agrees with or confirms the truthfulness or accuracy of the information. It should not be considered as investment advice from Webull or anyone else, nor should it be used as the basis of any investment decision.