U.S. Gold says CK Gold feasibility study shows after-tax NPV5% of $632 million
Share
Listen to the news
U.S. Gold says CK Gold feasibility study shows after-tax NPV5% of $632 million
  • U.S. Gold outlined financing talks for its fully permitted CK Gold project, targeting a construction decision in H2 2026.
  • March 2026 feasibility study: after-tax NPV5% USD 632 million, 27% IRR, 2.5-year payback, 11-year mine life, 20 kt/d.
  • At spot prices near USD 4,500/oz gold, after-tax NPV5% estimated at about USD 1.37 billion, payback about 1.6 years.
  • Initial capital estimated at about USD 394 million, excluding pre-production owners’ costs; major permits secured, site work started under industrial siting permit.
  • Company formed a special committee to assess M&A interest; evaluating a Keystone project spinout to limit dilution.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. U.S. Gold Corp. published the original content used to generate this news brief via PR Newswire (Ref. ID: 202608200805PR_NEWS_USPR_____SF30344) on August 20, 2026, and is solely responsible for the information contained therein.

Disclaimer:This article represents the opinion of the author only. It does not represent the opinion of Webull, nor should it be viewed as an indication that Webull either agrees with or confirms the truthfulness or accuracy of the information. It should not be considered as investment advice from Webull or anyone else, nor should it be used as the basis of any investment decision.