Denison Mines posts investor presentation on Phoenix ISR uranium mine construction progress and 2028 production target
Share
Listen to the news
Denison Mines posts investor presentation on Phoenix ISR uranium mine construction progress and 2028 production target
  • Denison highlighted full-scale construction at its Phoenix in-situ recovery uranium mine, targeting first production in 2028.
  • Phoenix civil works exceeded 20% completion by end-July 2026; total engineering about 90% complete.
  • Post-FID Phoenix capex estimated at CAD 600 million, implying total capex of about CAD 700 million including roughly CAD 100 million pre-FID.
  • Balance sheet cited at about CAD 625 million in cash, physical uranium, and investments as of June 30, 2026.
  • Physical uranium holdings totaled about 1.1 million lbs U3O8; 350,000 lbs sales fixed through Q2 2027 at US$ 95.17 per lb.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Denison Mines Corp. published the original content used to generate this news brief on August 20, 2026, and is solely responsible for the information contained therein.

Disclaimer:This article represents the opinion of the author only. It does not represent the opinion of Webull, nor should it be viewed as an indication that Webull either agrees with or confirms the truthfulness or accuracy of the information. It should not be considered as investment advice from Webull or anyone else, nor should it be used as the basis of any investment decision.