Lithium Americas targets Thacker Pass Phase 1 mechanical completion in late 2027, commercial output in 2028
Share
Listen to the news
Lithium Americas targets Thacker Pass Phase 1 mechanical completion in late 2027, commercial output in 2028
  • Lithium Americas outlined a path to Thacker Pass Phase 1 mechanical completion in late 2027, with ramp-up to commercial production in 2028.
  • Phase 1 targets 40,000 tonnes a year of battery-grade lithium carbonate; first full year of capacity expected in 2029.
  • Project funding highlighted: US DOE ATVM loan of US $2.23 billion with US $1.45 billion advanced to date.
  • General Motors investment totals US $945 million for a 38% JV interest, with a 20-year offtake for up to 100% of Phase 1 volumes.
  • Thacker Pass Phase 1 capex estimate cited at US $2.93 billion; 2026 capex guidance set at US $1.3-$1.6 billion.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Lithium Americas Corp. published the original content used to generate this news brief on August 21, 2026, and is solely responsible for the information contained therein.

Disclaimer:This article represents the opinion of the author only. It does not represent the opinion of Webull, nor should it be viewed as an indication that Webull either agrees with or confirms the truthfulness or accuracy of the information. It should not be considered as investment advice from Webull or anyone else, nor should it be used as the basis of any investment decision.