KEPCO targets Sept. 15 grid connection for Mihama nuclear Unit 3 after refueling outage review
Share
Listen to the news
KEPCO targets Sept. 15 grid connection for Mihama nuclear Unit 3 after refueling outage review
  • KEPCO set Sept. 15, 2026 for Mihama nuclear Unit 3 to reconnect to Japan’s power grid.
  • The 826-MW pressurized water reactor has been offline since a manual shutdown on May 8 due to high-pressure turbine steam leakage.
  • The 29th refueling outage began June 16; the revised timeline reflects progress on repairs and outage work.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. KEPCO - Kansai Electric Power Co. Inc. published the original content used to generate this news brief on September 01, 2026, and is solely responsible for the information contained therein.

Disclaimer:This article represents the opinion of the author only. It does not represent the opinion of Webull, nor should it be viewed as an indication that Webull either agrees with or confirms the truthfulness or accuracy of the information. It should not be considered as investment advice from Webull or anyone else, nor should it be used as the basis of any investment decision.
What's Trending