Ivanhoe Electric Santa Cruz copper PFS posts after-tax NPV8 of $3.5 billion at $6.79/lb copper
Share
Listen to the news
Ivanhoe Electric Santa Cruz copper PFS posts after-tax NPV8 of $3.5 billion at $6.79/lb copper
  • Ivanhoe Electric released a 2026 preliminary feasibility study for its Santa Cruz Copper Project in Arizona, forecasting first cathode production in 2029.
  • Study models initial capital of USD 1.43 billion with life-of-mine C1 cash costs of USD 1.47/lb copper.
  • At COMEX copper USD 6.79/lb, after-tax NPV at 8% totals USD 3.5 billion with a 30% IRR.
  • Base-case copper price USD 4.75/lb implies after-tax NPV at 8% of USD 1.52 billion with a 18.7% IRR.
  • Mine plan targets 75,000 tonnes average annual copper output for the first 15 years using a Robbins tunnel boring machine decline.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Ivanhoe Electric Inc. published the original content used to generate this news brief via Newsfile (Ref. ID: 202609230700NEWSFILECNPR____20260923_315570_1) on September 23, 2026, and is solely responsible for the information contained therein.

Disclaimer:This article represents the opinion of the author only. It does not represent the opinion of Webull, nor should it be viewed as an indication that Webull either agrees with or confirms the truthfulness or accuracy of the information. It should not be considered as investment advice from Webull or anyone else, nor should it be used as the basis of any investment decision.