Kyeryong Construction seeks to extend Icheon–Mungyeong rail contract term, drops end-date disclosure
Share
Listen to the news
Kyeryong Construction seeks to extend Icheon–Mungyeong rail contract term, drops end-date disclosure
  • Kyeryong Construction issued a correction to its single sales and supply contract disclosure for the Icheon–Mungyeong railway project, Section 6.
  • The revision removed the contract end date of 2026-09-30, citing ongoing talks to change the project period.
  • It plans to re-disclose once a revised contract is signed with the National Railroad Authority.
  • The contract value remains KRW 61.32 billion, equal to 2.69% of 2019 consolidated revenue.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Kyeryong Construction Industrial Co. Ltd. published the original content used to generate this news brief via DART, the regulatory disclosure system operated by the South Korea Financial Supervisory Service (FSS) (Ref. ID: 20260930800378), on September 30, 2026, and is solely responsible for the information contained therein.

Disclaimer:This article represents the opinion of the author only. It does not represent the opinion of Webull, nor should it be viewed as an indication that Webull either agrees with or confirms the truthfulness or accuracy of the information. It should not be considered as investment advice from Webull or anyone else, nor should it be used as the basis of any investment decision.