Norske Skog targets PM6 restart in 1H 2028 after Saugbrugs rockslide shutdown
Share
Listen to the news
Norske Skog targets PM6 restart in 1H 2028 after Saugbrugs rockslide shutdown
  • Norske Skog will rebuild paper machine PM6 at its Saugbrugs mill in Halden, targeting restart in H1 2028.
  • PM6 was taken out of service following a rockslide at Saugbrugs in April 2023.
  • The project is budgeted at up to NOK 850 million, enabling flexible output of TMP-based kraftliner or SC magazine paper.
  • Once PM6 starts, production on PM4 and PM5 is planned to be shut permanently, with deliveries expected to continue uninterrupted.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Norske Skog ASA published the original content used to generate this news brief on October 07, 2026, and is solely responsible for the information contained therein.

Disclaimer:This article represents the opinion of the author only. It does not represent the opinion of Webull, nor should it be viewed as an indication that Webull either agrees with or confirms the truthfulness or accuracy of the information. It should not be considered as investment advice from Webull or anyone else, nor should it be used as the basis of any investment decision.