i-80 Gold prioritizes Mineral Point open-pit project in updated Nevada development plan
Share
Listen to the news
i-80 Gold prioritizes Mineral Point open-pit project in updated Nevada development plan
  • I-80 Gold updated its Nevada development plan, keeping Archimedes underground and the Lone Tree plant refurbishment on schedule.
  • Archimedes is expected to start production mining in Q4 2026; Lone Tree construction is set for Q4 2026.
  • Lone Tree capital estimate remains USD 430 million; about 10% of contingency has been used, with first gold pour targeted in Q4 2027.
  • Mineral Point open pit was moved ahead of Granite Creek open pit; the March 2025 PEA outlined about 280,000 gold-equivalent ounces annually.
  • Production target remains 150,000 to 200,000 ounces from 2028; Mineral Point is expected to lift output to 400,000 to 500,000 ounces from 2031.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. I-80 Gold Corp. published the original content used to generate this news brief via CNW (Ref. ID: 202610140600CANADANWCANADAPR_C3782) on October 14, 2026, and is solely responsible for the information contained therein.

Disclaimer:This article represents the opinion of the author only. It does not represent the opinion of Webull, nor should it be viewed as an indication that Webull either agrees with or confirms the truthfulness or accuracy of the information. It should not be considered as investment advice from Webull or anyone else, nor should it be used as the basis of any investment decision.