-+ 0.00%
-+ 0.00%
-+ 0.00%
Dong-Ah Geological Engineering Raises Shield TBM Contract Value to 21.79 Billion Won
Share
Listen to the news
Dong-Ah Geological Engineering Raises Shield TBM Contract Value to 21.79 Billion Won
  • Dong-Ah Geological Engineering raised its Sanggye-Nowon power tunnel contract value to KRW 21.79 billion from KRW 21.52 billion.
  • The Oct. 16, 2026, correction extended completion to Dec. 30, 2027, from May 12, 2027.
  • The revised contract represents 6.3% of revenue, up from 6.2%.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Dong-Ah Geological Engineering Co. Ltd. published the original content used to generate this news brief via DART, the regulatory disclosure system operated by the South Korea Financial Supervisory Service (FSS) (Ref. ID: 20261016800813), on October 16, 2026, and is solely responsible for the information contained therein.

Disclaimer:This article represents the opinion of the author only. It does not represent the opinion of Webull, nor should it be viewed as an indication that Webull either agrees with or confirms the truthfulness or accuracy of the information. It should not be considered as investment advice from Webull or anyone else, nor should it be used as the basis of any investment decision.
What's Trending