ESGold surpasses 4,000 meters of drilling at Montauban project
Share
Listen to the news
ESGold surpasses 4,000 meters of drilling at Montauban project
  • ESGold has drilled approximately 4,074 meters at its Montauban project in Québec, exceeding 80% of its planned 5,000-meter program.
  • Drilling has expanded southward beyond historic mine workings, with a 600-meter hole planned to test deeper targets.
  • Core logging identified sulphide-bearing veins; laboratory assays are pending to establish metal grades.
  • Nineteen equipment containers are in transit from China; eight more are scheduled to depart this week for the Montauban processing facility.
  • The fully permitted tailings reprocessing project is advancing toward gold and silver production alongside exploration of the broader property.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. ESGold Corp. published the original content used to generate this news brief via ACCESS Newswire (Ref. ID: 202610200735ACCESSWRNAPR_____1238615) on October 20, 2026, and is solely responsible for the information contained therein.

Disclaimer:This article represents the opinion of the author only. It does not represent the opinion of Webull, nor should it be viewed as an indication that Webull either agrees with or confirms the truthfulness or accuracy of the information. It should not be considered as investment advice from Webull or anyone else, nor should it be used as the basis of any investment decision.