Wärtsilä Wins Order to Convert Termocabo Power Plant to Natural Gas in Brazil
Share
Listen to the news
Wärtsilä Wins Order to Convert Termocabo Power Plant to Natural Gas in Brazil
  • Wärtsilä secured an order to convert Brazilian utility Termocabo's power plant from heavy fuel oil to natural gas.
  • The order was booked in the third quarter of 2026.
  • The conversion enabled Termocabo to secure a 10-year contract to supply 50 megawatts to Brazil's national grid.
  • The project includes converting three engines and upgrading plant systems.
  • Commissioning is scheduled for July 2028.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Wärtsilä Oyj published the original content used to generate this news brief on October 26, 2026, and is solely responsible for the information contained therein.

Disclaimer:This article represents the opinion of the author only. It does not represent the opinion of Webull, nor should it be viewed as an indication that Webull either agrees with or confirms the truthfulness or accuracy of the information. It should not be considered as investment advice from Webull or anyone else, nor should it be used as the basis of any investment decision.