Namib Minerals Says Expanded Milling Plant At How Mine Is Now Operating At Its Full Rate Of ~55,000 Tonnes Per Month
Share
Listen to the news

Ramp-up completed well ahead of the six-to-eight-week timeline and the end-of-December target

NEW YORK, Oct. 26, 2026 (GLOBE NEWSWIRE) -- Namib Minerals ("Namib" or "the Company") (NASDAQ:NAMM), today announced that the expanded milling plant at How Mine has been commissioned and is now operating at its full rate of approximately 55,000 tonnes per month.

As disclosed in the Company’s first-half 2026 results on October 1, 2026, commissioning was expected in mid-October, followed by a ramp-up of approximately six to eight weeks, with the plant expected to reach its full rate by the end of December 2026.

Disclaimer:This article represents the opinion of the author only. It does not represent the opinion of Webull, nor should it be viewed as an indication that Webull either agrees with or confirms the truthfulness or accuracy of the information. It should not be considered as investment advice from Webull or anyone else, nor should it be used as the basis of any investment decision.
What's Trending