  • Bowman Consulting warned Virginia data center developers to revisit assumptions about fast-track permitting and older diesel backup generation under Executive Order 22.
  • Signed September 18, 2026, the order advances a framework requiring local approval for data centers using more than 25 MW.
  • The framework calls for developers to bear more grid costs and make stronger upfront financial commitments.
  • Projects with strong water stewardship, noise mitigation and clean backup power strategies will be better positioned for approval, Bowman said.
  • Virginia plans to seek legislation codifying the standards in the 2027 General Assembly session.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Bowman Consulting Group Ltd. published the original content used to generate this news brief on October 23, 2026, and is solely responsible for the information contained therein.

Disclaimer:This article represents the opinion of the author only. It does not represent the opinion of Webull, nor should it be viewed as an indication that Webull either agrees with or confirms the truthfulness or accuracy of the information. It should not be considered as investment advice from Webull or anyone else, nor should it be used as the basis of any investment decision.