Cloudberry's Odal wind farm resumes normal operations after turbine repairs
Share
Listen to the news
Cloudberry's Odal wind farm resumes normal operations after turbine repairs
  • Cloudberry Clean Energy’s Odal wind farm is operating normally following production disruptions; all turbines met return-to-service criteria in Q2 2025.
  • All material repairs are complete; Siemens Gamesa covered blade and other relevant component replacements under the existing service agreement.
  • Odal Vind signed a 10-year support agreement with Siemens Gamesa, starting when the original five-year service agreement expires in 2028.
  • The parties reached a final settlement covering outstanding project claims and the remaining construction payment obligation.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Cloudberry Clean Energy ASA published the original content used to generate this news brief via Cision (Ref. ID: 20261026:BIT:0136:0) on October 27, 2026, and is solely responsible for the information contained therein.

Disclaimer:This article represents the opinion of the author only. It does not represent the opinion of Webull, nor should it be viewed as an indication that Webull either agrees with or confirms the truthfulness or accuracy of the information. It should not be considered as investment advice from Webull or anyone else, nor should it be used as the basis of any investment decision.