Jentayu Sustainables Publishes SR
Share
Listen to the news
Jentayu Sustainables Publishes SR
  • Jentayu Sustainables’ Sustainability Report 2026 details an extension of 162 MW Project Oriole’s financial close deadline to June 30, 2027.
  • The hydropower project’s scheduled commercial operation date moved to December 31, 2030, from April 30, 2030.
  • Subscribers were secured for RM 560 million in redeemable preference shares; remaining project financing is being finalized.
  • Oriole’s provisional electricity tariff increased from 31.50 sen/kWh to 32.04 sen/kWh to address expanded construction-service taxes.
  • The proposed Jentayu Solar acquisition was dropped following shareholders’ rejection on December 4, 2025, leaving Oriole central to renewable energy growth.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Jentayu Sustainables Bhd published the original content used to generate this news brief via Bursa Malaysia (KLSE) (Ref. ID: 3721091) on October 30, 2026, and is solely responsible for the information contained therein.

Disclaimer:This article represents the opinion of the author only. It does not represent the opinion of Webull, nor should it be viewed as an indication that Webull either agrees with or confirms the truthfulness or accuracy of the information. It should not be considered as investment advice from Webull or anyone else, nor should it be used as the basis of any investment decision.