Lechwerke’s LVN expands Gundremmingen substation in EUR 30.5 million upgrade
Share
Listen to the news
Lechwerke’s LVN expands Gundremmingen substation in EUR 30.5 million upgrade
  • Lechwerke's LEW Verteilnetz is investing around EUR 30.5 million in upgrading Gundremmingen substation, with work underway since late September.
  • The expansion will increase capacity to handle regional renewable electricity, with commissioning planned for 2030.
  • An 80-MVA transformer, due in late July 2027, will triple transfer capacity between the 110-kV and 20-kV networks.
  • A 350-MVA transformer, due in May 2028, will double transfer capacity between the high-voltage and transmission networks.
  • A third busbar will improve operational flexibility, while replacement 20-kV switchgear will double existing capacity.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Lechwerke AG published the original content used to generate this news brief on November 03, 2026, and is solely responsible for the information contained therein.

Disclaimer:This article represents the opinion of the author only. It does not represent the opinion of Webull, nor should it be viewed as an indication that Webull either agrees with or confirms the truthfulness or accuracy of the information. It should not be considered as investment advice from Webull or anyone else, nor should it be used as the basis of any investment decision.