SSE brings first new turbine online in £80 million Lochay hydro upgrade
Share
Listen to the news
SSE brings first new turbine online in £80 million Lochay hydro upgrade
  • SSE returned the first new turbine generating unit to commercial operation under its £80 million refurbishment of Lochay Power Station in Perthshire.
  • The refurbishment will extend the 45MW station's operating life by at least 40 years, improving efficiency and output.
  • Unit 1 resumed generation in late September following its April 2025 shutdown; both units will be available for commercial operation over winter.
  • The station will shut in spring 2027 for Unit 2 refurbishment, including installation of the second new turbine generating unit.
  • Completion is expected in 2028, supporting modernization of the hydro fleet to maximize renewable generation from existing assets.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. SSE plc published the original content used to generate this news brief on November 06, 2026, and is solely responsible for the information contained therein.

Disclaimer:This article represents the opinion of the author only. It does not represent the opinion of Webull, nor should it be viewed as an indication that Webull either agrees with or confirms the truthfulness or accuracy of the information. It should not be considered as investment advice from Webull or anyone else, nor should it be used as the basis of any investment decision.