America’s Biggest Lithium Bet Just Got $900 Million Pricier
Share
Listen to the news

Lithium Americas Corp. (NYSE:LAC) stock fell Wednesday after the company raised its construction cost estimate for the Thacker Pass lithium project in Nevada by nearly $900 million.

The company announced the revised estimate Wednesday, ahead of its third-quarter earnings report.

Lithium Americas has pitched Thacker Pass as “America’s largest fully integrated source of domestic battery-quality lithium carbonate” and the nation’s “clearest near-term path to a reliable domestic supply.”

The project is backed by a federal Department of Energy loan and a joint venture with General Motors, and it employs nearly 2,000 workers at one of Nevada’s largest construction sites.

Thacker Pass Construction Costs Jump 31%

Lithium Americas increased its Phase 1 capital cost estimate to $3.83 billion from $2.93 billion, citing higher labor expenses, tariffs and logistics costs.

The roughly 31% increase reflects rising competition for skilled workers, higher installation costs and additional construction staffing requirements.

The company also added approximately $150 million in contingency funding to address remaining project risks.

Meanwhile, Lithium Americas raised its 2026 capital expenditure forecast to $1.7 billion-$2 billion from $1.3 billion-$1.6 billion.

Company Outlines $995 Million Funding Plan

Lithium Americas estimates it needs approximately $995 million in additional funding following the revised project cost assessment.

The company expects to cover the requirement through $650 million in contributions to its joint venture with General Motors and $315 million from existing U.S. Department of Energy loan reserve accounts.

Additionally, amendments to the federal loan agreement are expected to reduce certain reserve funding requirements by approximately $30 million.

As of Sept. 30, Lithium Americas held approximately $1.3 billion in cash and restricted cash, including $359.5 million at the joint venture.

Production Timeline Remains Unchanged

Despite higher costs, Lithium Americas maintained its construction schedule.

The company expects mechanical completion of Thacker Pass Phase 1 in late 2027, followed by production ramp-up in 2028.

Once fully operational, the facility is designed to produce approximately 40,000 metric tons of battery-quality lithium carbonate annually.

Moreover, engineering work is complete, while equipment and materials procurement has surpassed 90%.

CEO Jonathan Evans said the company remains focused on completing construction and transitioning Thacker Pass into commercial production.

Earnings Ahead

Investors will now turn their attention to Lithium Americas’ third-quarter earnings report, scheduled for Friday, Nov. 13.

LAC Price Action: Lithium Americas shares were down 7.52% at $1.74 at the time of publication on Wednesday, according to Benzinga Pro data.

Image via Shutterstock

Disclaimer:This article represents the opinion of the author only. It does not represent the opinion of Webull, nor should it be viewed as an indication that Webull either agrees with or confirms the truthfulness or accuracy of the information. It should not be considered as investment advice from Webull or anyone else, nor should it be used as the basis of any investment decision.