Bauer completes Canada’s deepest soil-mixing wall at Fraser Mills residential project
Share
Listen to the news
Bauer completes Canada’s deepest soil-mixing wall at Fraser Mills residential project
  • Bauer Foundations Canada completed a CAD 7.4 million excavation-support and groundwater cut-off wall for Fraser Mills Encore in Coquitlam, British Columbia.
  • Construction ran from May to August 2026, producing Canada's deepest cutter soil mixing wall at up to 40.5 meters.
  • The residential project includes a 32-story tower with 306 homes within Beedie Living's approximately 39-hectare Fraser Mills redevelopment.
  • Foundation work includes 185 continuous flight auger piles reaching 28.5 meters, with installation scheduled to begin in December 2026.
  • The broader waterfront development plans around 5,500 homes on the former sawmill site.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Bauer GmbH & Co. KgaA published the original content used to generate this news brief on November 13, 2026, and is solely responsible for the information contained therein.

Disclaimer:This article represents the opinion of the author only. It does not represent the opinion of Webull, nor should it be viewed as an indication that Webull either agrees with or confirms the truthfulness or accuracy of the information. It should not be considered as investment advice from Webull or anyone else, nor should it be used as the basis of any investment decision.