Fervo Energy Executes New 105 MW Transmission Service Agreement With Longroad Energy For Cape Station Development In Beaver County, Utah
Share
Listen to the news
  • New 105 MW agreement builds on the company's existing grid-connected transmission rights, providing over 500 MWs of firm transmission rights for Cape Station.
     

HOUSTON, Nov. 18, 2026 (GLOBE NEWSWIRE) -- Fervo Energy (NASDAQ:FRVO), a global pioneer of next-generation geothermal energy, today announced it has executed a new 105 Megawatt (MW) Transmission Service Agreement (TSA) with Longroad Energy for its Cape Station development in Beaver County, Utah.

The agreement gives the company long-term, firm delivery rights on the Milford Gen Lead line and builds on the parties' existing 400 MW arrangement, bringing Cape Station's total contracted long-term firm transmission capacity to 505 MW. This new capacity provides a strong foundation for Cape’s continued growth.

The new TSA is expected to begin in 2028, subject to final regulatory approvals.

Disclaimer:This article represents the opinion of the author only. It does not represent the opinion of Webull, nor should it be viewed as an indication that Webull either agrees with or confirms the truthfulness or accuracy of the information. It should not be considered as investment advice from Webull or anyone else, nor should it be used as the basis of any investment decision.