Google (GOOGL.US) is investing over $500 million in the next generation of geothermal energy! Bernstein is optimistic about industry prospects Fervo (FRVO.US) and Ormat (ORA.US) are expected to benefit
Share
Listen to the news

The Zhitong Finance App learned that Google (GOOGL.US) signed a 50-megawatt long-term electricity purchase agreement (PPA) with US geothermal energy startup Quaise Energy, and plans to start supplying electricity to Google's data centers as early as 2030. According to reports, the total value of the agreement is over $500 million. Bernstein pointed out in a research report released on November 17 that this deal is an important milestone in the commercialization of next-generation geothermal technology. It not only reflects the tech giants' urgent need for all-weather clean energy, but also brings a positive signal to the entire geothermal energy industry.

Bernstein believes that as demand for electricity in artificial intelligence (AI) data centers continues to grow, clean energy that can be stably supplied around the clock is becoming increasingly scarce, and advanced geothermal technology is expected to become an important way to solve this problem.

Google bets on ultra-high temperature geothermal technology

Under the agreement, Quaise Energy will supply 50 megawatts of electricity to Google's three data center campuses in The Dalles through the Project Obsidian project located near Mount Newbury in central Oregon, USA, and delivery will begin as early as 2030.

Quaise is a private geothermal energy technology developer from the Massachusetts Institute of Technology (MIT), dedicated to generating electricity using thermal energy in ultra-high temperature rock layers. Unlike traditional geothermal technology, Quaise is developing a millimeter-wave drilling technology based on gyrotron (Gyrotron). The technology was initially applied to nuclear fusion research. It uses high-energy millimeter waves to heat and melt rock instead of cutting rock layers with traditional mechanical drills, which can be expected to drill deeper and hotter underground regions.

Bernstein pointed out that Quaise has raised about US$280 million so far, including US$180 million in Series B financing completed in August of this year, of which the oilfield drilling equipment company Nabors (NBR.US) participated as a strategic investor of 35 million US dollars.

However, Quaise is currently still in the technical verification stage and does not yet have a power well officially put into commercial production. The agreement signed with Google is also the company's first commercial power purchase contract, so Project Obsidian will be a key project to test the commercial viability of its technology.

According to the plan, the first phase of the project mainly uses traditional drilling technology, drilling to a depth of about 2.5 miles, and then plans to use millimeter wave technology to further drill to about 3 miles. The second phase plans to commercialize millimeter-wave drilling technology for the first time.

Bernstein cautioned that the first stage of power generation did not rely entirely on millimeter-wave technology, so investors should not start supplying televisions in 2030 as this new drilling technology has already been commercially verified.

The 50 MW project invested about 350 million US dollars, and the electricity purchase price is still in doubt

In terms of economy, Project Obsidian is expected to require about US$350 million in capital expenditure, which is equivalent to approximately US$7,000 per kilowatt of installed capacity.

Bernstein pointed out that this construction cost is roughly comparable to the cost of Fervo Energy's Cape Station Phase I project and some projects announced by Ormat Technologies, and it is also significantly lower than the first batch of nuclear power projects using new technology.

However, Google and Quaise did not disclose the specific electricity price, contract period, and payment structure of the electricity purchase agreement, so the outside world is still unable to accurately determine the actual electricity price corresponding to this transaction of more than 500 million US dollars.

Based on a capacity factor of about 85%, Bernstein estimates that a 50 MW project can produce about 370 million to 400 million kilowatt-hours of electricity per year. If the total contract is calculated at $500 million, assuming that the term of the electricity purchase agreement is 10 years, the corresponding average electricity price is about $130 per megawatt hour; if the contract period is 15 years, the electricity price is about $90; if the term is extended to 20 years, it is about $65.

Bernstein believes that since ultra-high temperature geothermal is a new technology that has not been fully verified, the initial construction cost is high, so the actual contract pricing may be at a relatively high level. However, the agency also stressed that these figures are only calculated based on scenarios based on different contract periods. They cannot be directly regarded as the actual electricity purchase price paid by Google, nor should they be used to measure the electricity price level of the entire geothermal industry.

Ultra-high temperature geothermal potential is huge, but commercialization still faces triple challenges

Bernstein believes that the biggest potential advantage of ultra-high temperature geothermal technology is the power generation capacity of a single well. Quaise claims its technology is expected to generate 10 times more electricity from a single geothermal well than a traditional geothermal well. If this goal is finally achieved, the unit cost of generating ultra-high temperature geothermal heat is likely to drop rapidly as the technology matures and the scale of the project expands.

However, if the actual production capacity of a single well is only comparable to existing enhanced geothermal systems (EGS), then Quaise's project is probably just a geothermal development solution with deeper drilling, more complex rock formation conditions, and higher costs.

Bernstein specifically pointed out that the future success of the project mainly depends on three key factors. The first is the actual performance of underground reservoirs. Reaching the target temperature is only the first step. How to maintain stable flow in a high-temperature environment close to a supercritical state, control the drop in reservoir pressure, and ensure long-term reliable operation of the borehole and related equipment is a greater technical challenge.

The second is whether millimeter-wave drilling technology can be scaled up. Since the first phase still mainly relies on traditional drilling equipment, Bernstein believes that millimeter wave technology should be viewed as a potential growth opportunity for the second phase and should not be included in the basic assumptions of power generation in early 2030.

The third is power transmission capacity. The project required the construction of approximately 10 miles of transmission lines to connect electricity to the La Pine substation, and then transport it north through the regional grid to Google's data center in The Dalles. Due to the limited expansion of the local transmission network, the ability to ensure stable transmission is also an important uncertain factor.

As a result, Bernstein believes that although Google's power purchase agreement reduces the project's future revenue risk, it does not eliminate the risks related to underground resource development, technical verification, and transmission infrastructure.

Bernstein is optimistic that Fervo and Ormat will maintain target prices of $47 and $112

Although Quaise itself has not yet been listed, Bernstein believes that Google's deal will have a positive impact on the entire next-generation geothermal energy industry. Among them, Fervo Energy (FRVO.US) and Ormat Technologies (ORA.US) are worth watching.

Regarding Fervo, Bernstein believes that Google continues to sign geothermal power purchase agreements, indicating that large technology companies are incorporating geothermal energy into long-term power supply strategies. Currently, Google has signed a 396 megawatt power purchase agreement with Fervo, and the commercialization progress of Fervo's Cape Station project is clearly ahead of Quaise.

Bernstein pointed out that Cape Station's first 33-megawatt power module was put into commercial operation on October 1, and the remaining installed capacity of the first phase is expected to be put into operation one after another in 2027.

In contrast, Quaise's 50 MW project won't start supplying electricity until 2030 at the earliest, so the two do not form a direct short-term competition.

Bernstein believes that Google is actually building a geothermal energy portfolio covering different technology routes and delivery times, and Fervo is still in an advantageous position with earlier commercialization progress and relatively mature technology.

The agency maintains Fervo's “outperforming the market” rating and a target price of $47. Based on the closing price of $10.98 on November 16, the potential upside corresponding to the target price is about 328%.

Regarding Ormat, Bernstein believes that Google's continued investment in advanced geothermal technology has also verified the direction of the geothermal industry's upgrading to a new generation of technology.

Ormat is currently working with Sage Geosystems to test a technology that combines geothermal power generation and energy storage, and is also piloting another technology with Schlumberger (SLB.US).

Bernstein believes that these projects will help Ormat participate in the development of new geothermal technologies and further expand potential business opportunities.

The agency maintains Ormat's “in sync with the market” rating and a target price of $112. Based on the closing price of $89.32 on November 16, the corresponding potential upside is about 25%.

AI power demand pushes geothermal energy to usher in new opportunities

Bernstein pointed out that although the 50 megawatt power purchase agreement signed by Google this time is small, its strategic significance cannot be ignored.

As AI data centers continue to expand, large technology companies need not only more electricity, but also energy that can be supplied stably around the clock while meeting low carbon emission targets.

Compared with wind energy and solar energy, which are more affected by weather and day/night changes, geothermal power generation can provide stable electricity for 24 hours, so it has certain scarcity and potential premium capacity.

Google has previously proposed the goal of providing all-weather carbon-free energy by 2030, and signing a contract with Quaise this time is another step in expanding its clean energy procurement portfolio.

Bernstein believes that in regions with high clean energy requirements, large data center operators are facing the problem of insufficient stable supply of carbon-free electricity, so they may be willing to take the risk of commercializing some new technologies in order to lock in future energy supply ahead of time.

This will not only help secure financing and commercial orders for next-generation geothermal technology, but may also further enhance the market value of existing stable clean energy assets.

However, Bernstein emphasized that the Quaise project is still a long-term bet on drilling technology and underground reservoir types that have not been fully proven. Google has the ability to take on early technological risks, but this does not mean that the relevant technology is ready for large-scale commercialization.