NSW appoints Transgrid to deliver and operate Hunter Transmission Project
Share
Listen to the news
NSW appoints Transgrid to deliver and operate Hunter Transmission Project
  • NSW appointed Transgrid as Hunter Transmission Project network operator, responsible for delivery, long-term operations and maintenance.
  • Construction contracts went to Downer for transmission lines and UGL for substations; construction is scheduled to begin next year.
  • The 110-kilometer, 500 kV double-circuit overhead line will add 5 GW of electricity transfer capacity.
  • The project will connect Central-West Orana and New England renewable energy zones, enabling access to cheaper renewable power as coal generation retires.
  • Delivery is expected to create 900 construction jobs; EnergyCo will retain planning and oversight responsibilities.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. TransGrid - Electricity Transmission Ministerial Holding Corporation published the original content used to generate this news brief on November 23, 2026, and is solely responsible for the information contained therein.

Disclaimer:This article represents the opinion of the author only. It does not represent the opinion of Webull, nor should it be viewed as an indication that Webull either agrees with or confirms the truthfulness or accuracy of the information. It should not be considered as investment advice from Webull or anyone else, nor should it be used as the basis of any investment decision.