i-80 Gold starts production mining at Archimedes underground project
Share
Listen to the news
i-80 Gold starts production mining at Archimedes underground project
  • i-80 Gold has started production mining on schedule at Archimedes in Nevada, its second underground mine to enter production.
  • Total project capital is expected to exceed the USD 47.3 million preliminary estimate by approximately USD 10 million following infrastructure upgrades.
  • Oxide material is being heap-leached at Ruby Hill, with initial gold recovery expected in the first quarter of 2027.
  • Refractory material will be stockpiled for processing at Lone Tree, scheduled for commissioning in the fourth quarter.
  • Combined annual gold production from Archimedes and Granite Creek is targeted at 150,000–200,000 ounces beginning in 2028.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. I-80 Gold Corp. published the original content used to generate this news brief via CNW (Ref. ID: 202611231812CANADANWCANADAPR_C8915) on November 23, 2026, and is solely responsible for the information contained therein.

Disclaimer:This article represents the opinion of the author only. It does not represent the opinion of Webull, nor should it be viewed as an indication that Webull either agrees with or confirms the truthfulness or accuracy of the information. It should not be considered as investment advice from Webull or anyone else, nor should it be used as the basis of any investment decision.