PTPP's North Sumatra Road Recovery Project Reaches 82.53% Completion, Ahead of Target
Share
Listen to the news
PTPP's North Sumatra Road Recovery Project Reaches 82.53% Completion, Ahead of Target
  • PTPP's post-disaster road rehabilitation project in North Sumatra reached 82.53% completion as of November 24, 2026, ahead of target.
  • The joint-operation contract is worth Rp 268.66 billion, covering the Aceh border–Sibolga and Rampa–Poriaha/Mungkur road sections.
  • Work covers 31 landslide sites across 131 kilometers under a design-build contract with a 396-calendar-day execution period.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. PT Pembangunan Perumahan (Persero) Tbk published the original content used to generate this news brief via Indonesia Stock Exchange (IDX) (Ref. ID: 60f7d85b-fe2f-4b26-b115-ed935c05c117) on November 26, 2026, and is solely responsible for the information contained therein.

Disclaimer:This article represents the opinion of the author only. It does not represent the opinion of Webull, nor should it be viewed as an indication that Webull either agrees with or confirms the truthfulness or accuracy of the information. It should not be considered as investment advice from Webull or anyone else, nor should it be used as the basis of any investment decision.
What's Trending