The US energy approval reform bill “breaks through” the House of Representatives next week, and the AI power chain is betting on a “definitive dividend” to be realized, ushered in a critical moment
Share
Listen to the news

The Zhitong Finance App learned that the US Senate passed the 2026 Bipartisan Affordability and Employment Act (BAAJA) by 62 votes to 33 on November 19 and sent this nearly 500-page licensing reform bill to the House of Representatives. House Speaker Mike Johnson (Mike Johnson) plans to push for a vote as soon as the week of November 30 after the Thanksgiving recess.

Since the bill also touches on approval rules for transmission lines, gas pipelines, data centers, and clean water, and the White House has expressed “strong support,” every move affects the pace of investment in AI energy infrastructure. According to analysis by various agencies, there is still a fierce battle between the three outcomes of passing as is, passing with conditions, and being stranded to the new National Assembly.

AI data centers are written into the core of licensing reform

BAAJA's most direct impact on AI infrastructure is the formal inclusion of data centers in the scope of application of the federal licensing reform. The bill's amendments to the National Environmental Policy Act (NEPA) cover a wide range of projects such as transmission lines, renewable energy facilities, mines, pipelines, and data centers; provisions specific to data centers include excluding telecommunications utilities that provide internet and cable services, and requiring disclosure of data center licensing and authorization information.

What has received more attention is the “fast track” effect. A letter co-signed by more than 120 legal scholars to House leadership indicates that large-scale pollution projects such as data centers and gas pipeline expansion “can be built with almost no review of their hazards” under BAAJA, and may facilitate the construction of data centers on federal public land. The letter also quoted an impressive set of data as saying that if the largest proposed data center gas power plant is implemented, nine of the ten largest power plants in the US will serve data centers; the carbon footprint of America's existing largest data center is close to that of Denmark. However, during the review, the Senate vetoed an amendment to “prohibit the construction of data centers on federal land” proposed by the Democratic Party, which means that data center construction on federal land has not been blocked.

Notably, the direction of the bill's exemption from broadband contrasts with the tightening of data centers. BAAJA created NEPA exemptions for federally funded cable projects that have analyzed transit rights, and exempted upgrades to existing fiber-optic lines from NEPA review — the result of broadband industry lobbying with joint support from more than 50 state industry associations and operators, including AT&T (T.US) and Verizon (VZ.US). In other words, the same law unbinds “networks that transmit data,” and gives both green light and conditions to “computing power that consumes electricity.”

Why now: AI electricity consumption curve hits approval bottleneck

The reason why BAAJA is receiving a lot of attention from the market at this point is that US electricity demand is being driven into a historic round of growth by AI data centers. The short-term energy outlook updated by the US Energy Information Administration (EIA) in October predicts that electricity consumption across the US will rise from a record 4.195 trillion kilowatt-hours in 2025 to 4.288 trillion kilowatt-hours in 2026 and 4.356 trillion kilowatt-hours in 2027, continuously reaching new high levels, and the growth rate has remained above 1.5% for the past three years. The EIA further predicts in its “Annual Energy Outlook 2026” that the share of electricity used by data center servers in the US commercial sector will rise from about 7% in 2025 to 22% to 33% in 2050.

The increase on the planning side is steeper: According to statistics from the research agency Grid Strategies, the peak summer load forecast for the next five years has risen from 24 gigawatts in 2022 to 166 gigawatts in 2025, which is close to seven times the previous seven times. Of these, about 90 gigawatts are related to data centers (the agency also suggests that some projects may not be completed as scheduled, and there is a risk of overestimation in load forecasting). Goldman Sachs's forecast is more aggressive. It estimates that US data center electricity demand will increase from 31 gigawatts in 2025 to 41 gigawatts in 2026 and 66 gigawatts in 2027, nearly doubling within two years.

However, the pace on the supply side is seriously mismatched. According to the data quoted in the legal scholar's letter mentioned above, additional heavy loads such as data centers can be built in 1 to 2 years, and a large transmission line often takes 6 to 10 years; Lawrence Berkeley National Laboratory estimates that the share of electricity used in data centers will rise from 4.4% in 2023 to 6.7% to 12% in 2028. As a result, the speed of approval has become a “stuck neck” link in the expansion of AI computing power — this is where BAAJA is trying to leverage.

Grid and grid-connected reforms are the main line in the medium to long term

If you only look at the review time frame, BAAJA's weight may be overestimated. The analysis points out that BAAJA's significance for solar energy and energy storage is not mainly to shorten the federal environmental review, because according to a survey by Columbia University's Center for Global Energy Policy in February 2026, 80% of clean energy developers deliberately avoid federal permits during the site selection phase. What is really important is two points: first, the bill provides legal protection for approved projects, reduces the risk of policy intervention, and improves financing conditions; second, it pushes forward transmission and grid connection reforms to ease the hard restrictions on medium- to long-term deployment.

The bill is heavily inscribed on both of these lines. According to Shanghai Metal Network (SMM), in terms of power transmission, if a state does not act within a year, the Federal Energy Regulatory Commission (FERC) can approve transmission lines of 230 kV and above; regional and cross-regional transmission plans established by FERC Order 1920 will be written into law, costs will be shared in proportion to benefits, and state policy goals will not be included in benefit estimates. In terms of grid connection, the plan is to switch to cluster research and introduce non-refundable deposits and exit penalties. Each region must announce connected sites with fixed access costs; newly built energy storage facilities within existing road rights can be exempted from NEPA and historical protection reviews. In addition, FERC must initiate rule-making within one year to study the use of artificial intelligence and automation to process grid-connection applications, and each region must submit joint plans for power generation, load and transmission within two years.

The review time frame was also rewritten. The environmental impact assessment (EA) must be completed within 1 year, the environmental impact report (EIS) must be completed within 2 years, and the agency must make a decision record within 45 days after the final EIS; the time limit for challenges against NEPA was shortened from a maximum of 6 years to 150 days, and the case was directly appealed to the Federal Court of Appeals. If there are only flaws in the NEPA process, the court cannot revoke the license or issue an injunction, and must be sent back to the agency for correction within 180 days. Holland & Knight added that the Senate amendments limit the protection of approved projects to those that have been finally approved.

According to SMM's judgment, the effects of the transmission and grid connection provisions will not gradually become apparent until 2028, coinciding with the opening of the US solar tax credit window. At that time, US PV deployment will depend more on construction costs and licensing and grid connection speed — and the latter is the direction BAAJA is aiming for.

Solar energy and energy storage: Determinism over speed

For the clean energy industry, BAAJA's core value is “certainty” rather than “acceleration.” The American Solar Energy Industry Association (SEIA) estimates that more than 500 solar and energy storage projects, totaling nearly 116 gigawatts (73 gigawatts of photovoltaics, 43 gigawatts of energy storage), face the risk of political intervention due to incomplete federal, state, or local licenses, which is about half of the new installed capacity planned by the US before 2030. Earlier, in July 2025, the US Department of the Interior required that photovoltaic wind power licenses involving federal land or Department of the Interior resources be approved by the Secretary's Office and extended to private land projects requiring crossing public land or involving wildlife and wetland consulting — 143 solar companies claimed in an open letter that caused an “almost complete suspension” of licensing.

BAAJA's policy risk hedging addresses this kind of situation — section 1401 of the Act prohibits agencies from revoking, suspending, or amending federal licenses effective on or after September 16, 2026, unless there is a court order, material breach, fraud, or emergency damage based on new information; section 1402 allows project parties to sue for “differential treatment” for certain types of projects, with compensation of up to 50% to 100% of the anticipated construction costs. The 47 types of energy and mining projects protected include photovoltaics, onshore wind power, and offshore wind power. The US government suspended five offshore wind power projects on national security grounds in December 2025 (later blocked by the court), which was an example of such risk.

SEIA estimates that compared to current law, BAAJA will increase the net installed capacity of 167 gigawatts (AC side) in the US from 2028 to 2035, and boost the share of solar power generation to 18.1% in 2035. However, the benefits of energy storage are more clear: according to the “Greater and American Act” that came into effect in July 2025, photovoltaics and wind power must be started before July 4, 2026 or put into operation before the end of 2027 to enjoy tax credits, while energy storage credits will continue until 2033 before they are gradually phased out. Combined with the review exemptions within existing road rights, energy storage “benefits more”.

However, BAAJA addresses licensing and grid integration, not trade policies. US imports of photovoltaic modules and batteries are still subject to anti-dumping and countervailing duties (AD/CVD), section 232 polysilicon measures that came into effect on December 4, section 301 overcapacity tariffs proposed on November 25, and “feoc” (FEOC) restrictions in tax credits; if the bill becomes law, the new demand will mainly flow to sources of production capacity and low trade barriers in the US, with limited direct boost to module exports from China and Southeast Asia.

House vote preview: three paths and a closed window of time

What really determines the fate of BAAJA is the voting path that the House of Representatives has yet to decide. House Speaker Mike Johnson (Mike Johnson) has two options: one is to go to the “suspension of the rules” (suspension of the rules) vote, which requires a two-thirds majority and prohibits amendments; the other is to go through the ordinary rules procedure, where the Rules Committee first passes a rule and then a simple majority vote. The House Rules Committee announced on November 25 (Wednesday) that it will meet on Monday (November 30) to review the bill, and it may be voted on that day or week as soon as possible.

The prospects for the “Suspend the Rules” path are not promising. Since many unelected Republican lawmakers stopped actively attending after the midterm elections, the House of Representatives even cancelled several votes last week due to insufficient attendance; even if all Republicans came together and voted in favor, it would still take about 71 Democrats to defy to round up two-thirds. Meanwhile, the Democratic Party in the House of Representatives is clearly divided: the leadership of the “New Democratic Party” made up of 114 centrists has initially endorsed it. California Representative Scott Peters (Scott Peters) said the bill “fits the country's current needs” and “the transmission provisions are better than expected”; however, the nearly 100-member Congressional Progressive Party has officially opposed it, and California Representative Jared Huffman (Jared Huffman) advocates waiting for the New Congress to control both houses before seeking a better text. Majority leader Steve Scalise (Steve Scalise) expressed support on November 20. Minority leader Hakeem Jeffries (Hakeem Jeffries) previously called the Senate text “still insufficient,” but also expressed “commitment to implementing licensing reforms.”

Time pressure is another constraint: the House of Representatives is scheduled to adjourn the current session of the National Assembly on December 17, and the 119th National Assembly will end on January 3, 2027; the government funding deadline of December 11 is also vying for the remaining parliamentary time. According to an analysis by a conservative think tank, out of 11 cases of “waiting for a better bill” in history, only 3 ended up waiting for better results, all of which took more than two years. If the House of Representatives makes any amendments to the Senate text, the bill must be returned to the Senate for another vote — a sharp increase in difficulty under such a compressed schedule. Senate bill drafters are still pushing for an amendment to improve tribal provisions: requiring tribal negotiations regardless of whether federally funded projects require federal approval, and increasing the annual authorization of state and tribal historical preservation offices by $100 million to $300 million; they tend to attach this amendment to “must pass” laws such as government funding proposals before December 11.

Opposition comes from the three fronts of tribal rights, clean water protection, and judicial restrictions, and is not limited to rating disputes. The bill narrows the scope of application of section 106 of the National Historic Preservation Act and restricts tribal negotiation procedures. It was opposed by 11 tribes and senators, and is accused of threatening tribal sovereignty; in terms of clean water, the bill makes it more difficult for states to establish pollution protection, extends mandatory license review from 5 to 10 years and reduces transparency. Environmental organizations warn that scientific updates are blocked and favors the oil and gas industry; the system reserves permanent licenses, taxpayer compensation to developers, and provisions such as “closing court doors”. The legislation lacks hearing, review and reporting, and has left more than 150 cases unamended. Its “affordability” selling point has also been questioned: the annual savings of 50 to 78 US dollars will be achieved by 2040, and another estimate of 250 dollars. The gap is large and all are predictions.

Based on information from various sources, the forward-looking judgment is that passing the Senate text as it is is still the “cleanest”, least resistant path, and is endorsed by the White House; following ordinary rules and passing it by a simple majority is more likely than a “suspension rule”; and once substantial tribal or environmental amendments are added, the probability that the bill will need to be reintroduced into law in the current session of the National Assembly has declined significantly, and is more likely to continue to be re-proposed in the new Congress until 2027.

Institutional opinion: Geothermal and power grid equipment has been named, and investment banks say it is beneficial to cover the sector

Bernstein ranked the benefits in the November 19 research report: Geothermal energy is the most direct, followed by transmission networks and power grid equipment, gas pipelines, and liquefied natural gas (LNG) projects, which benefit from increased approval certainty, while the benefits of renewable energy and nuclear power are relatively limited and take longer to be reflected. The bank emphasized that the core significance of the bill is to simultaneously ease multiple electricity supply bottlenecks, but the direct impact on the profits of relevant enterprises in 2027 is expected to be limited. The specific logic of geothermal optimism is that exploration and test wells are exempt from NEPA approval and enjoy licensing treatment similar to oil and gas. Federal land geothermal lease tenders were changed from once every two years to once a year, and drilling licenses use a “30 day plus 30 day” processing mechanism.

At the individual stock level, Bernstein gave Fervo Energy (FRVO.US) a “outperforming the market” rating, a target price of $47, Ormat Technologies (ORA.US) “in sync with the market” rating, and a target price of $112; maintaining GE Vernova (GEV.US) “outperforming the market” with a target price of $1,298, and NextEra Energy (NEE.US) “outperforming the market”, and a target price of $108, Cheniere Energy ( LNG.US) “outperforms the market” with a target price of $312; Bloom Energy (BE.US) received “in sync with the market” and a target price of $306, which is regarded as an indirect beneficiary of the self-built power scheme. Regarding data centers, Bernstein specifically pointed out that the bill requires data centers to bear the full cost of transmission services and cannot be passed on to other users. The previous 20 megawatt threshold has been abolished — this will increase the economic appeal of self-built or locally supporting power generation, but the bank still believes that connecting to a public grid is the first choice for most data centers.

J.P. Morgan Chase expressed an overall positive opinion in the latest “Clean Energy Weekly Tearsheet”: the bank believes that if BAAJA is passed, the overall composition of the sector it covers will be beneficial. The provisions sorted out in the research report include expanding FERC's construction licensing rights for interstate transmission lines, renewable energy, geothermal, hydropower, and offshore energy projects, “rate taxpayer protection” for large-scale computing loads such as data centers, and the establishment of a new Department of Energy data center community assistance program to help local authorities assess the energy, water, and economic impacts of data center development.

However, Xiaomo also pointed out that its covered stocks fell by an average of about 18.9% last week, outperforming the S&P 500 (down 8.6%). Among them, “overrated” Generac (GNRC.US) and IDEX (ITRI.US) bucked the trend, while T1 Energy (TE.US), which had a “neutral” rating, plummeted by 42.4% — indicating that policy expectations were not immediately transformed into sector markets.

Conclusion: AI power investment welcomes a “definitive dividend” but is still betting on an undecided vote

The impact of BAAJA on the construction of AI energy and power facilities can be summed up in one sentence: it brought not an immediate effect on the speed of approval, but a reassessment of policy certainty. For data centers, while providing a fast track, the bill requires public licensing and “fair sharing” of grid costs; for power grids and grid connections, it enshrines FERC Order 1920 into law and introduces cluster research and AI to assist approval, but the results will not be until 2028; for photovoltaics and energy storage, it uses sections 1401 and 1402 to cover licensed projects to reduce policy risk premiums and improve financing conditions.

If the House of Representatives passes it as it is and signed by the President before the end of the current Congress, US PV and energy storage will first benefit from increased project certainty — approved projects face lower risks of cancellation and differential treatment, and financing and construction plans are more predictable; while the effects of shortening the review period and grid-connection reforms will have to be implemented. They are expected to become apparent after 2028, partially offsetting the drag on installations due to the expiration of the solar tax credit. Conversely, if the House of Representatives amends the text or does not vote in the current session of the National Assembly, the bill will have to be re-introduced in the new Congress, and uncertainty about federal licensing for photovoltaic and energy storage projects will continue. For investors betting on the AI power chain, the vote in the week of November 30 decided whether this “definitive dividend” can be realized.